TL;DR - Key Takeaways
- Factory Acceptance Testing (FAT) is your last chance to catch defects before the machine ships from China. Once it arrives at your facility, fixes become exponentially more expensive and harder to enforce.
- Never accept a no-load-only test. No-load tests cannot verify output capacity, mixing quality, or actual production performance. You must test with your material.
- Plan 1-3 days on-sitefor standard Twin Screw Extruders. Complete compounding lines may require 3-5 days.
- Five red flags that must stop the shipment: output below 90% of rated, temperature instability exceeding plus/minus 5 degrees C, vibration above 4.5 mm/s RMS, safety system failures, or manufacturer refusing load testing.
- Documentation is as critical as the test itself. Incomplete FAT paperwork creates customs delays, warranty disputes, and insurance complications.
Introduction: Why I Wrote This Guide
In my 10 years managing international equipment deliveries for JURRY Extrusion, I have witnessed factory acceptance testing prevent disasters that would have cost buyers hundreds of thousands of dollars to fix after delivery. I have also, more painfully, watched buyers skip FAT or conduct it so poorly that critical defects sailed right through undetected.
The case that haunts me most happened in 2019. A first-time buyer in Nigeria, excited about his new compounding line, decided to skip on-site FAT to save roughly USD 5,000 in travel costs. He reasoned: "The manufacturer has ISO 9001. They are professional. It will be fine." Three months after the machine arrived in Lagos, the gearbox failed catastrophically. When I investigated, I discovered the gearbox ratio was wrong - the manufacturer had built the machine to an older quote, not the revised order. Because no FAT had been conducted, there was no documentary evidence of when the error occurred. Resolving that situation cost the buyer USD 38,000 in replacement parts, USD 12,000 in emergency air freight, and 7 weeks of lost production. His USD 5,000 "savings" turned into a USD 50,000 lesson.
I share this story not to scare you, but because I have seen it repeat in variations across Southeast Asia, East Africa, the Middle East, and Latin America. Because the distance between buyer and manufacturer is so vast, post-delivery problem resolution is categorically harder than with a domestic supplier. By the time a defect discovered in your facility gets communicated, investigated, and remediated, you have already missed production windows, broken contracts with your own customers, and exhausted goodwill with your team.
FAT is not a bureaucratic formality. It is your single most powerful quality control mechanism in an international equipment purchase. It is your last opportunity to verify - while the manufacturer is still financially and operationally motivated to fix issues - that the machine you paid for is the machine that shows up at your dock.
This guide gives you everything you need to conduct effective FAT on twin screw extruders. I have built this from JURRY's own FAT procedures, industry best practices from ISO 15546, ISO 10816, and lessons from over 300 international deliveries I have personally overseen or supported.
Section 1: Understanding What FAT Really Is - And What It Is Not
Before we go further, let me define terms clearly, because confusion here causes real problems.
FAT (Factory Acceptance Testing) is conducted at the manufacturer's facility, before the machine is shipped. Its purpose is to verify that the machine as built matches the purchase order specifications and performs within agreed acceptance criteria.
SAT (Site Acceptance Testing) is conducted at the buyer's facility, after installation. SAT verifies that the machine was installed correctly, that local utilities (power, water, compressed air) are adequate, and that the machine performs in its actual production environment.
I have seen buyers confuse these two - expecting FAT to catch installation issues, or believing SAT is unnecessary if FAT was thorough. Because your factory environment is different from the manufacturer's test floor, SAT is always required regardless of FAT completeness. The manufacturer's test conditions (stable power, controlled ambient temperature, their preferred test material) will never perfectly match your production floor.
Section 2: Pre-FAT Preparation - Where Success Is Actually Won
If I could give only one piece of advice about FAT, it would be this: your preparation determines the quality of your FAT, not the test day itself. I have accompanied dozens of buyers through FATs, and the ones who catch the most issues are always the ones who arrived with the most preparation.
2.1 Documentation Package Review (Begin 3-4 Weeks Before Travel)
Request these documents from the manufacturer no later than three weeks before you plan to travel. Do not accept vague promises - these documents either exist or they do not, and their absence tells you something important:
Pre-FAT Documentation Checklist
- Mechanical drawings: Screw element sequence drawing, barrel cross-section, heating zone layout, flange connections
- Electrical schematics: Power distribution single-line diagram, control system architecture, safety circuit schematic
- Material certificates:Mill certificates for Screw And Barrel materials per ASTM A370; hardness test reports; heat treatment records
- Component datasheets: Motor nameplate data, gearbox rating certificate, heater band specifications, thermocouple type confirmation
- Gearbox test report: Should show no-load current, oil temperature rise, and noise level
- FAT protocol draft: Manufacturer's proposed test procedure - review this carefully and negotiate changes
- Manufacturing inspection records: In-process inspection logs, welding records (if applicable), assembly check-off sheets
2.2 Define Your Acceptance Criteria in Writing (Before Travel)
This step is non-negotiable. Before you arrive at the factory, you must have written, agreed acceptance criteria signed by both parties. Vague criteria like "machine runs well" have no legal standing:
| Parameter | Acceptance Threshold | Measurement Method |
|---|---|---|
| Output capacity | Greater than or equal to 95% of rated output | Weigh output over 30-minute run |
| Melt temperature stability | Plus/minus 3 degrees C at die exit, steady state | Calibrated thermocouple, 10-minute recording |
| Screw speed accuracy | Plus/minus 1% of setpoint | Optical tachometer verification |
| Motor current at full load | Less than or equal to 85% of rated current | Clamp-on amp meter |
| Vibration level | Less than or equal to 4.5 mm/s RMS per ISO 10816 | Vibration meter at bearing housings |
| Noise level | Less than or equal to 85 dB(A) at 1 meter | Sound level meter, A-weighted |
| Die head pressure | Stable, within rated limit | Installed pressure transducer |
2.3 Prepare Your Test Material (2 Weeks Before FAT)
This is where I see the most shortcuts taken, and it is always a mistake. The manufacturer's standard test material - usually general-purpose PP or PE - tells you almost nothing about how your specific formulation will process.
In 2018, I worked with a compounding company in Kenya that was producing glass-filled nylon for automotive parts. The manufacturer ran FAT with PP, and the machine performed beautifully. When the buyer tried to run their actual formulation - 30% glass-filled PA66 - they got catastrophic output instability and the screws jammed within 20 minutes. The reason: the compression ratio of the screw configuration was wrong for the higher-viscosity material. Because the load test was done with the wrong material, a fundamental design incompatibility was completely hidden.
Ship 50-100 kg of your actual production material to the manufacturer at least two weeks before FAT. Label it clearly with your formulation code, target melt temperature, and moisture sensitivity classification. If your material requires pre-drying, confirm the manufacturer has appropriate drying equipment.
Section 3: The FAT Protocol - Step by Step
Follow this sequence. Every step builds on the previous one. I have seen buyers try to skip the no-load test to "save time" - that is exactly when mechanical problems get missed.
3.1 Day 1 Morning: Documentation Review and Walkdown
Before touching any equipment, spend two to three hours reviewing documents and comparing them to what you ordered. This catches specification mismatches before you waste time testing the wrong machine:
Document vs. Purchase Order Verification
- Motor power and speed match PO?
- Gearbox ratio and rating match PO?
- Screw diameter and L/D ratio match PO?
- Barrel zone configuration match PO?
- Control system brand and specs match PO?
- All documentation in your language or bilingual?
- CE / UL / CSA compliance certificates provided (if required)?
3.2 Day 1 Afternoon: Mechanical and Visual Inspection
Now inspect the machine itself. Bring a flashlight, a mirror on a flexible handle, and a camera. Some of the most important things to check are in places that are hard to see:
Mechanical Inspection Checklist
- Screw elements: Remove a sample element and verify geometry matches drawing; check for machining marks, burrs, or surface defects; measure root diameter of at least one element
- Barrel bore: Visually inspect bore surface; if possible, measure with an internal bore gauge
- Barrel wear: New barrels should show wear less than 0.02mm; excessive wear indicates the machine was used for testing with abrasive material
- Heating zones: Count actual zones and compare to documentation; inspect heater band physical condition
- Thermocouples: Verify type (J, K, or PT100) matches specification
- Gearbox: Check oil sight glass - oil should be clear, not milky; check for oil leaks around seals
- Motor: Verify nameplate data: power (kW), speed (rpm), voltage, frequency, frame size
- Coupling: Inspect coupling condition and alignment marks
- Electrical panel: Verify component brands match specification (contactors, VFDs, PLC); check wire labeling
- Safety guarding: All rotating shafts and couplings must have guards; verify guard interlock switches
- Grounding: Verify grounding straps on motor and electrical panel
- Surface finish: Check paint or powder coat quality; for stainless steel components, verify proper passivation
- Nameplates: Machine nameplate with serial number, model, year of manufacture
3.3 Day 2 Morning: No-Load Running Test
The no-load test verifies mechanical operation without material. It is not optional, and it is not sufficient on its own - but it is critical. Running the machine without material first lets you identify mechanical problems safely and at lower risk:
No-Load Running Test Checklist
- Startup sequence: Verify all pre-start interlocks and warnings function; machine should not start unless all guards are closed
- Low speed test (20% max): Run for 5 minutes; listen for unusual noise; check for vibration
- Mid speed test (50% max): Run for 10 minutes; measure vibration at motor, gearbox, and barrel support positions
- High speed test (80% max): Run for 10 minutes; monitor bearing temperatures every 5 minutes
- Maximum speed test (100% max): Run for 5 minutes; verify no resonant vibration; record maximum speed achieved
- Temperature monitoring: Record bearing housing temperatures at start and end of each run; temperature rise should not exceed 40 degrees C above ambient
- Current draw: Record no-load current at each speed; typical no-load current is 15-25% of rated full-load current
- Screw direction: Confirm correct rotation direction per the specification (co-rotating or counter-rotating)
- Emergency stop test: While running at 50% speed, activate E-stop; verify stopping time is within specification (typically less than 5 seconds)
- Restart after E-stop: Verify machine cannot restart until E-stop is reset
3.4 Day 2 Afternoon to Day 3: Load Test with Material
This is the most important part of FAT. No-load tests tell you the machine is mechanically sound. Load tests tell you whether the machine can actually do the job you bought it for.
I have been in factories where the manufacturer pushed back hard on load testing - "The material you sent is not ready," "We do not have the right die," "We prefer to use our standard material." Every time, there was a reason. Some reasons were legitimate. Some were not. If the manufacturer cannot or will not conduct load testing with your actual material, you should not accept shipment.
Load Test with Material Checklist
- Material preparation: Verify material moisture content; for hygroscopic materials (PA, PET, etc.), confirm proper drying before feeding
- Die installation: Install the correct die for your application; if your order did not include a die, use the standard slit die for output testing
- Feeding system calibration: Verify feeder operates correctly; check for material bridging or erratic flow
- Cold startup with material: Start at low speed and low feed rate; gradually increase to target parameters over 20-30 minutes
- Steady-state output measurement: Collect extrudate for exactly 30 minutes; weigh accurately; calculate kg/h; repeat at 3 different screw speeds (minimum, middle, maximum rated)
- Melt temperature recording: Record die exit melt temperature every 5 minutes for at least 30 minutes of steady operation
- Die head pressure: Monitor and record pressure; verify it stays within safe operating limits
- Motor load: Record motor current at each output measurement point; verify stays below 85% of rated current
- Extrudate quality inspection: Examine extrudate for: bubbles (indicates moisture), discoloration (indicates degradation), uneven diameter (indicates flow instability), black specs (indicates contamination or wear)
- Long-duration stability run: Run at rated output for minimum 2 hours continuously; record all parameters every 15 minutes
- Shutdown and purge: Verify clean shutdown procedure; inspect screw and barrel for material residue and signs of wear after purge
3.5 Day 3 Morning: Safety System Verification Under Load
Safety systems must be tested under actual operating conditions - not just by pressing buttons while the machine is stopped. A safety interlock that works in static test but fails under vibration and temperature is worthless:
Safety System Verification Checklist
- E-stop under load: Press emergency stop while machine is running at 50% load; verify safe and immediate stop; measure stopping time
- Over-temperature protection: Simulate over-temperature condition on one zone; verify heater shuts off and alarm sounds
- Motor overload relay: Verify motor overload relay trips at specified current setting
- Feeder-extruder interlock: Stop the feeder suddenly; verify extruder responds correctly (should reduce speed or stop)
- Guard door interlocks: Attempt to open guard door while machine is running at low speed; verify machine stops immediately
- Pressure relief device: If a pressure relief valve or rupture disc is installed, verify it is set at the correct pressure and is unobstructed
- Fire suppression: If a fire suppression system is included, verify it is properly charged and the pull cable or actuator is accessible
Section 4: Documentation - Your Legal Record and Your Warranty
The test itself is only half of FAT. Documentation is the other half, and I have seen excellent tests become nearly worthless because the paperwork was incomplete. Here is what you must receive:
4.1 FAT Report - Minimum Required Contents
FAT Report Checklist
- Cover page: Machine model, serial number, purchase order number, FAT date, factory location, buyer and manufacturer representatives with signatures
- Test equipment list: All measurement instruments used, with model numbers and calibration certificates
- Test data sheets: Every measured value from every test, signed by both buyer and manufacturer representatives on each page
- Deviation register: Any deviation from specification found during FAT, with agreed corrective action and completion date
- Outstanding issues list: Any items not completed during FAT and the timeline for resolution
- Acceptance declaration: Clear statement: either "FAT Passed - Shipment Authorized" or "FAT Conditional - Shipment Pending Resolution of Issues Listed Above"
- Photographs: Key machine views, nameplates, and all defects found
Never sign a blank or incomplete FAT report. I have heard stories - and I mean stories because no one admits to it happening to them - of buyers signing attendance sheets that later became "acceptance certificates." Make sure the document you sign clearly states what was tested, what the results were, and what the acceptance status is.
4.2 Complete Documentation Package
Documentation Package Checklist
- Operation manual in English (or your language)
- Maintenance manual with preventive maintenance schedule
- Electrical as-built drawings (not design drawings - actual "as built" with any changes made during assembly)
- Mechanical assembly drawings with parts list
- Spare parts list with part numbers and recommended stock quantities
- Material certificates for screw and barrel
- Motor and gearbox test certificates
- Calibration certificates for all temperature controllers and pressure transducers
- Warranty document with clear terms and contact information
- Packing list with weights, dimensions, and photographs of crated machine
Section 5: Red Flags - When to Stop Shipment
Some issues discovered during FAT are serious enough that you must not accept the machine until they are fully resolved. Know when to hold firm. The pressure to accept and ship will be real - manufacturers have production schedules, and delays cost them money too but the cost of accepting a defective machine is almost always higher than the cost of delaying shipment.
- Output capacity less than 90% of rated specification - after proper load testing with your material
- Temperature control instability exceeding plus/minus 5 degrees C from setpoint
- Vibration levels exceeding 4.5 mm/s RMS at any bearing housing
- Abnormal noise (knocking, grating, squealing) at any speed
- Safety systems failing to operate correctly under test conditions
- Motor, gearbox, or other major component not matching PO specification
- Manufacturer refuses to conduct load testing with your material
- Incomplete or missing critical documentation (material certs, test certificates, manuals)
- Barrel or screw showing signs of previous heavy use (excessive wear on new machine)
When issues are found, document them thoroughly and get written commitment from the manufacturer on:
- Exactly what the problem is
- What corrective action will be taken
- Who is responsible for the correction
- By what date the correction will be completed
- Who will verify the correction is complete
Section 6: Post-FAT Actions - Do Not Relax Yet
FAT completion is not the end of your responsibility. Proper follow-up ensures the machine arrives safely and is ready for efficient installation:
Before Shipment
- Verify corrective actions: If any issues were found during FAT, confirm they are corrected before crating; request photographs if you cannot re-attend
- Review packing plan: Ensure the machine will be packed for ocean freight - sea air is corrosive, and improper packing has destroyed machines in transit
- Confirm insurance: Arrange marine cargo insurance for the CIF value of the shipment
- Verify shipping documents: Commercial invoice, packing list, bill of lading, certificate of origin, and FAT report
During Shipment
- Track your shipment: Monitor vessel arrival and estimated arrival at destination port
- Prepare your site: Foundation, utilities, lifting equipment, and installation team should be ready before the machine arrives
- Prepare customs: Have all import documentation ready to avoid port storage charges, which accumulate fast
After Arrival
- Inspect immediately: Before signing the delivery receipt, inspect the crate for visible damage; photograph everything
- Compare to packing list: Verify all items listed on the packing list are present before the freight forwarder leaves
- Document shipping damage: If any damage is found, photograph it immediately and file a claim with the freight forwarder before the container is emptied
- Commissioning: Use FAT data as your baseline - if SAT results differ significantly from FAT results, investigate why before accepting the installation
Section 7: Special Considerations by Application
7.1 Masterbatch and Color Compounding
If you are buying an extruder for masterbatch production, pay special attention to mixing uniformity during load testing. Request a pigment dispersion test - extrude a sample and check color uniformity under a microscope or through a filter test (ISO 1855 for carbon black dispersion). I have seen extruders pass output tests but produce poorly dispersed color concentrates that failed customer quality checks.
7.2 Glass Fiber Reinforced Compounds
For glass-filled materials, verify that the barrel and screw are properly hardened for abrasive wear. Check the barrel bore for any signs of previous wear or scoring. After FAT, inspect the screw elements for glass fiber adhesion - excessive fiber buildup indicates processing issues that will affect product quality and throughput.
7.3 Medical or Food-Grade Applications
For medical or food-contact applications, FAT must include verification of material contact surface finish (Ra values), documentation of cleaning validation, and verification of any required certifications (FDA, EU 10/2011, etc.). The FAT protocol for these applications should be more stringent and include surface roughness measurements, passivation verification, and system cleanliness inspection.
7.4 High-Temperature Engineering Polymers
If you are processing high-temperature polymers (PPS, PEEK, LCP), the FAT protocol must include extended preheating cycles to verify thermal stability of all zones, verification that barrel heating capacity is sufficient for your target melt temperatures, and testing at actual processing temperatures - not just at the manufacturer's standard test temperatures.
Section 8: Frequently Asked Questions
Conclusion: FAT Is Your Power - Use It
FAT is not a bureaucratic formality or a box-ticking exercise. It is your most powerful quality control mechanism in an international equipment purchase. When I look back at the hundreds of FATs I have supported or overseen, the ones that went smoothly were always the ones where the buyer arrived prepared, followed the protocol systematically, and held firm when issues were found.
The temptation to accept a machine quickly - to clear it and let it ship so you can get on with your project - is real. Manufacturers know this, and some will apply subtle pressure to skip items or sign off before testing is complete. Resist that pressure. The cost of a thorough FAT in time and travel is trivial compared to the cost of a defective machine in your facility.
If you are evaluating twin screw extruders from Chinese manufacturers and would like support planning your FAT, or if you want JURRY to walk you through our FAT procedures before you commit to an order, contact me through our website at JURRY Extrusion or connect with me on LinkedIn. I am always happy to discuss your application and help you understand what to look for - whether you end up buying from us or not.










